Submitted by: Submitted by santhu9953754
Views: 167
Words: 90802
Pages: 364
Category: Other Topics
Date Submitted: 01/16/2014 09:10 PM
PMP Question Bank
(1440 Questions)
Question Set 1
Total Questions: 10 + 10 + 25 + 10 + 11 + 10 + 26 + 15 = 117
1. Your developer has provided u with an estimate based on the “cost per line of code”. What type of estimate did the developer use to provide this information? A. Parametric estimating. B. Bottom-up- estimating. C. Analogues estimating. D. PERTestmating . 2. A definitive estimate is: A. Top-down estimating. B. Created during initiation. C. Within a range of -10% to +25% of actual. D. The most expensive to create. 3. all of the following are inputs to the cross-budgeting process expect? A. cost estimate. B. project schedule. C. risk management plan. Deactivate duration estimates. 4. Analogues estimating is a tool technique used in both Time and Cost management process. What is the best description of how analogues estimating is performed? A. by-buttom-up estimating techniques. B. obtaining management option’s of the estimate of each task. C. by-top-down estimating techniques. D. based on historical costs. 5. Cost budgeting is defined as A. the estimated total cost of the Project when done. B. allocating the cost estimates to the individual work items. C. developing estimates of the cost of the resources needed to complete project activities. D. the sum of the approved cost estimates. 6. Due to recent company downsizing u can only authorize 1 of the 2 projects u really planed to complete this year. You have decided to select the project with the NPV of $95k and proceed to cancel the other project which had an NPV of $37k what are the opportunity costs associated with this new decision? A. $37k B. $95k C. $123k D. $58k 7. Analogues estimating is a form of A. earned value. B. expert judgment. C. cost planning D. parametric modeling. 8. Two projects have exactly the same pay back period but project A has a smaller IRR than project B.You should choose
A. project A. B. project B C. there is no difference D. there is not enough information available...