Timeline of Milestones
Early 1995
Aug - Dec‘95
Jan ‘96
May ‘95
July ‘96
Aug ‘96
Dec ‘96
Sep ‘96
NIBCO could not prosper with its current IS
Gary Wilson hired as head of IS Department
Restructured corporation into cross-functional matrix organization
BCG conducted strategic IT planning study
Signed Contract with SAP for R/3 modules & IBM as implementation partner
ERP Selection Team recommended purchase of SAP R/3 & “Big Bang” Implementation
Final project scope and resource estimates presented to ELT and Board of Directors.
Go Live Date: 29 Nov 1997
Completed Project Team Selection
Begin Preparation Phase
Mar ‘97
May ‘97
Nov ‘97
Apr ‘97
Summer ‘97
Dec ‘97
Sep ‘97
v
Completed installation of PCs for Customer Service Associates.
Initiated weekly newsletter via email.
Business Review lead for Materials Management replaced by lead for production planning.
Decision to consolidate warehouses from 17 to 4 by Sept
Maintenance of legacy systems discontinued except for emergency repairs
User Training began.
Sandbox practice system becomes available.
Go Live date moved to Dec 30 due to delays
BIG BANG
Challenges
Pre-implementation efforts
* Proper analysis and planning
* Purpose and target must be well set and communicated
Project Team composition
* Leader with strong leadership qualities
* Other competent team members chosen from the various functional areas
* Suitable implementation partner
Keeping within the Time and Budget
ERP implementations can take years to complete and the process can be delayed or derailed by faulty planning and execution. Businesses rarely remain static, and requests for changes in scope during the project can get out of control.
* Difficult to keep within the forecasted time and budget
- Project may overrun
- Cost may increase
Complexity in consolidating many...