Chapter 9
Project Scheduling: PERT/CPM
Case Problem: R.C. Coleman
1. R.C. Coleman's Project Network
[pic]
|Activity |Expected Time |Variance |
|A | 6 |0.44 |
|B | 9 |2.78 |
|C | 4 |0.44 |
|D |12 |7.11 |
|E |10 |1.00 |
|F | 6 |0.44 |
|G | 8 |7.11 |
|H | 6 |0.44 |
|I | 7 |2.78 |
|J | 4 |0.11 |
|K | 4 |0.44 |
| |Earliest |Latest |Earliest |Latest | |Critical |
|Activity |Start |Start |Finish |Finish |Slack |Activity |
|A | 0 | 3 | 6 | 9 |3 | |
|B | 0 | 0 | 9 | 9 |0 |Yes |
|C | 9 | 9 |13 |13 |0 |Yes |
|D |13 |17 |25 |29 |4 | |
|E |13 |13 |23 |23 |0 |Yes |
|F |23 |23 |29 |29 |0 |Yes |
|G |13 |21...