DONNER COMPANY
Case Analysis
Group AG1
Aryan Jain (13610)
Hamza Umar (13627)
Nikita Jain (13632)
Parth Shah (13635)
Preetinisha (13637)
INTRODUCTION
Donner Company was started in 1985. Since the start of operations, it had specialized in making circuit boards for experimental devices and for pilot production runs. Edward Plummer was the President and Bruce Altmeyer was the firm's Design Engineer. The manufacturing process involved production of circuit boards known in the trade as "soldermask over bare copper"(SMOBC) boards .Edward Plummer is reviewing the position of the company in 1987 so that operations for 1988 can be planned effectively.
ORDER PROCESSING
The flow diagram of Donner’s order processing process is shown below:
Prepare a bid for customers/clients
Promise Delivery in 3 weeks
Send Specifications and documents to purchasing agents
Order Size>1000?
Rush Order or Normal Order?
Log Blueprint & factory order sent to supervisor
Estimate Labour and Material Costs
No Order Processing
Bid Accepted?
No
YES
NORMAL
RUSH
Promise Delivery in 5 weeks...