Planning and Managing Software Projects 2010-11

Session 5

Scheduling

Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza

http://emanueledellavalle.org

Credits

2

This slides are partially based on CEFRIEL’s slides for PMI Certification and largely based on Prof. John Musser class notes on “Principles of Software Project Management” Original slides are available at http://www.projectreference.com/ Reuse and republish permission was granted

Planning and Managing Software Projects – Emanuele Della Valle

Today

Session 4 review Scheduling Fundamentals Scheduling Techniques

• Network Diagrams • Bar Charts

3

Schedule Optimization Techniques Mythical Man-Month

Planning and Managing Software Projects – Emanuele Della Valle

Session 4 Review

WBS Estimation

4

Planning and Managing Software Projects – Emanuele Della Valle

Session 4 Review

WBS

Types: Process, Product, Hybrid Formats: Outline or graphical organizational chart High-level WBS does not show durations and dependencies WBS becomes input to many things, esp. schedule What hurts most is what’s missing 100% Rule:

• the sum of the work on the children must be equal to 100% of the work referred by the parent • no work outside the scope of the project is in the WBS

5

Planning and Managing Software Projects – Emanuele Della Valle

Session 4 Review

Estimation

6

Estimation is the process of determining the effort and the duration of activities Setting realistic expectations is the single most important task of a project “Unrealistic expectations based on inaccurate estimates are the single largest cause of software failure.”

• Futrell, Shafer, Shafer, “Quality Software Project Management”

Planning and Managing Software Projects – Emanuele Della Valle

Session 4 Review

Estimation

Use multiple methods if possible

• This reduces your risk • If using “experts”, use two

7

History is your best ally

•...