PART 1 : DATA
1. Product : Tenda Pramuka (Price Rp 300.000/ Unit)
2. Workers : 4 Person
3. Maximum working hours : 10 hours per day
4. Time estimated for produce 1 unit : 2,5 hours
5. Working days / month : 23 days = 230 hours / month
6. Maximum capacity / worker : 92 unit Tenda Pramuka per month per worker
7. Sewing cost : Rp 15.000 per unit Tenda Pramuka
8. Sewing cost overtime : Rp 25.000 per unit Tenda Pramuka
9. Subcontract (Min 50 Unit) : Rp 30.000 per unit Tenda Pramuka
10. Raw Material : D600DINIR, 1 Roll price = Rp 430.000,
1 Roll is for 6 Tenda Pramuka,
Raw material cost for 1 unit Tenda Pramuka :
Rp 430.000 / 6 = Rp 72.000
11. Inventory holding cost : Rp 5000
12. Hiring and training cost : Rp 500.000
13. Layoff cost : Rp 1.000.000
14. Safety stock : 10% of month demand
15. Beginning Inventory : 110 unit
|Month |Sales |Month |Sales |
|January |175 |July |260 |
|February |185 |August |280 |
|March |185 |September |300 |
|April |198 |October |300 |
|May |210 |November |290 |
|June |230 |December |260 |
16. Sales Data for year 2013 (Jan-Dec) : :
PART 2 : FORECASTING
Demand forecasting is the activity of estimating the quantity of a product or service that consumers will purchase. There is several method to forecast the demand. I use Linear Regression and Simple Moving Average method to forecast Tenda Pramuka 2014 sales/ demand.
Linear Regression Analysis :
[pic]
3-Month Moving Average :...