III. C. Schedule Feasibility

TASKS | START DATE | END DATE | DURATION | PREDECESSORS | MILESTONES | DELIVERABLES |

  |   |   |   |   |   |   |

1. Initiation Phase | | | | | | |

1.1 Background of the Study | October 1, 2014 | October 4, 2014 | 4 days | none | Problem Identified | Problem Identification Report |

  | | | | | | |

1.2 Statement of the Objectives | October 6, 2014 | October 11, 2014 | 6 days | none | Identified Project Title and Scope | Project Identification and Goals and Objectives Report |

  | | | | | | |

1.3 General Objective | October 13, 2014 | October 18, 2014 | 6 days | 1.1, 1.2 | GeneralIdentified | Finished \ the general Objective |

  | | | | | | |

1.4 Proposed System Procedural Diagram | October 20, 2014 | October 22, 2014 | 3 days | 1.3 | Proposed System Identified | Finished Proposed System Diagram |

  | | | | | | |

2. Analysis Phase | | | | | | |

2.1 Legal Feasibility | | | | | | |

2.1.1 Technical Feasibility | October 23, 2014 | October 25, 2014 | 3 days | 1.4 | Technical Feasibility Identified | Technical Feasibility Report |

  | | | | | | |

2.1.2 Operational Feasibility | October 27, 2014 | Nov 3, 2014 | 8 days | 1.3 | Operational Feasibility Identified | Operational Feasibility Report |

  | | | | | | |

2.1.3 Schedule Feasibility | Nov 4, 2014 | Nov 10, 2014 | 10 days | 1.3 | Schedule Feasibility Identified | Schedule Feasibility Report |

  | | | | | | |

2.1.4 Economic Feasibility | Nov 11, 2014 | Nov 15, 2014 | 5 days | 2.1.1 | Economic Feasibility Identified | Economic Feasibility Report |

  | | | | | | |

2.2 Requirement Specification | | | | | | |

2.2.1 Requirements Identification and Analysis | Nov 17, 2014 | Nov 19, 2014 | 3 days | 1.4 | Preliminary Requirements Identified | Preliminary Requirements Report |

  | | | | | | |...