Tijuana Bronze Manufacturing
Question 1
Valves Pumps Flow Controllers
Material $16.00 $20.00 $22.00
Direct Labor $4.00 $8.00 $6.40
($16 per hour * run labor per unit)
Overhead $17.55 $35.10 $28.08
(439% of Direct Labor)
Standard Unit Cost $37.55 $63.10 $56.48
Overhead calculation:
Receiving $20,000
Materials Handling $200,000
Engineering $100,000
Packing and Shipping $60,000
Maintenance $30,000
Machine Depreciation (10 year life) $270,000
Set-up Labor $2,688
(168 hours * $16 per hour)
Total $682,688
Total Run Labor: $155,600
(9,725 hours * $16 per hour)
Overhead rate: 438.75%
(682,688/155,600)
Question 2
Valves Pumps Flow Controllers
Revenue $57.78 $81.26 $97.07
Material Cost $16.00 $20.00 $22.00
Direct Labor Cost $4.00 $8.00 $6.40
Contribution Margin: $37.78 $53.26 $68.67
Question 3
Valves Pumps Flow Controllers
Material $16.00 $20.00 $22.00
Material Related Overhead $7.69 $9.61 $10.57
Set-up Labor $0.02 $0.05 $0.48
($16*set-up labor/monthly prod*runs)
Run Labor $4.00 $8.00 $6.40
Other $21.30 $21.30 $8.52
Revised Standard Cost: $49.00 $58.95 $47.97
Material Related:
Receiving $20,000
Handling $200,000
Total $220,000
(220,000/458,000) = 48.03%
Other:
Engineering $100,000
Packing and Shipping $60,000
Maintenance $30,000
Machine Depreciation (10 year life) $270,000
Total $460,000
[460,000/10,800 (total machine hours)] $42.59 per hour
Question 4
Valves Pumps Flow Controllers
Material $16.00 $20.00 $22.00
Labor $4.00 $8.00 $6.40
Overhead:
Setup $0.02 $0.05 $0.48
Receiving $0.08 $0.30 $3.90
Handling $0.80 $3.04 $39.00
Packing and Shipping $0.32 $1.10 $10.95...