Cost Management
1
IT projects have a poor track record for
meeting budget goals
The CHAOS studies found the average cost
overrun (the additional percentage or dollar
amount by which actual costs exceed
estimates) ranged from 180 percent in 1994 to
43 percent in 2010
A 2011 Harvard Business Review study reported
an average cost overrun of 27 percent.
2
The U.S. government, especially the IRS, continues to
provide examples of how not to manage costs
◦ A series of project failures by the IRS in the 1990s cost
taxpayers more than $50 billion a year
◦ In 2006, the IRS was in the news for a botched upgrade to its
fraud-detection software, costing $318 million in fraudulent
refunds that didn’t get caught
The United Kingdom’s National Health Service IT
modernization program was called the greatest IT
disaster in history with an estimated $26 billion
overrun. It was finally scrapped in 2011.
3
Cost is a resource sacrificed or foregone to
achieve a specific objective or something given
up in exchange
Costs are usually measured in monetary units
like dollars
Project cost management includes the
processes required to ensure that the project is
completed within an approved budget
4
5
Planning cost management :determining the
policies, procedures, and documentation that will
be used for planning, executing, and controlling
project cost.
Estimating costs: developing an approximation or
estimate of the costs of the resources needed to
complete a project
Determining the budget: allocating the overall
cost estimate to individual work items to establish
a baseline for measuring performance
Controlling costs: controlling changes to the
project budget
6
Reserves
◦ dollars included in a cost estimate to mitigate cost
risk by allowing for future situations that are
difficult to predict
◦ Contingency reserves
allow for future situations...