1. (TCO 4) The priority rule, which will sequence jobs in the order they are received, is _____. (Points : 5)
2. (TCO 2) In an assignment method problem, if it takes Abe 3 hours to build a birdhouse and 4 hours for a doghouse, and Betty takes 4 hours for a birdhouse and 3 hours for a doghouse, what is the reduced cost (in hours) of assigning Betty to build the doghouse? (Points : 5)
3. (TCO 2) A major difference between manufacturing and service systems in terms of scheduling is (Points : 5)
4. (TCO 3) Scheduling in service systems may involve scheduling which of the following?
(Points : 5)
5. (TCO 5) The owner and operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received:
Job Processing Time (hrs) Due (hrs from now)
-------------------------------------------------------------------------------------------------
If he uses the earliest due date first (EDD) priority rule to schedule these jobs, what will be the average job tardiness? (Points : 5)
6. (TCO 6) Building up an inventory of standard parts or modules instead of immediately producing the finished end items is the essence of (Points : 5)
7. (TCO 7) With regard to suppliers, JIT systems typically require (Points : 5)
8. (TCO 10) Which of the following is characteristic of the JIT philosophy? (Points : 5)
9. (TCO 1) In make-to-stock systems, fluctuations in sales volume are managed through which of the following? (Points : 5)
10. (TCO 5) In an MRP master schedule, the planning horizon is often separated into a series of times periods called (Points : 5)...