|1. |Final Part B Written Question - 60 minutes |
| |1. List each of the 6 steps required to have a successful FAT and equipment acceptance before shipping. 2. Write a |
| |summary of each of these steps. |
| | |
| | |
| | |
| |Student Response: |
| |1. There are six steps required to have a successful FAT before shipping 1. FAT protocol preparation. 2. FAT Execution|
|...