Name Duration start date Finish_Date

WBS # TASKS

1.0 measure rooms to place bid on project 7/5

1.1 Measure rooms

1.1.1 Figure square footage of all rooms

1.1.2 Figure price for labor and materials

1.1.3 Obtain approval for project

1.1.4 Order materials

2.0 room preparation

2.1 demolition of rooms

2.1.1 Remove old carpet

2.1.2 Remove old fixtures

2.1.3 Remove old dry wall

2.1.4 Clean up

2.1.5 Communicate readiness of room to electricians

3.0 electrical

3.1 electrical work

3.1.1 remove old fixtures

3.1.2 Map out where new fixtures go

3.1.3 Drill any holes needed to run the new wire

3.1.4 Measure for wire runs

3.1.5 Install new fixtures

3.1.6 Run new wires

3.1.7 Obtain electrical inspection

3.1.8 Fix anything the inspector finds

3.1.9 Communicate rooms readiness to dry wallers

4.0 dry walling

4.1 prep rooms for dry walling

4.1.1 Mark studs

4.1.2 makes sure all nails are out of walls and ceiling

4.1.3 Remove any remaining nails

4.1.4 Assure that there are no floating corners

4.1.5 Measure for board to be cut

4.1.6 Double check measurement

4.1.7 Check for fixtures that need to be cut out

4.1.8 Cut out any fixture holes

4.1.9 Apply glue

4.1.10 installs board

4.1.11 secure board

4.1.12 repeat tell done

4.1.13 communicate rooms readiness to finisher/painter

5.0 painting/finishing room 1, 2 and 3

5.1.1 Check dry wall job to make sure no floating corners

5.1.2 Contact dry wallers to fix anything needed to be fixed

5.1.3 Mix dry wall mud

5.1.4 Load banjo for taping seems

5.1.5 Take all horizontal seems

5.1.6 Tape one side of all corners

5.1.7 Dry time (around two hours)

5.1.8 Tape all vertical seems

5.1.9 Tape the other side of all corners

5.1.10 dry time (around two hours)

5.1.11 mix dry wall mud for second coat

5.1.12 second coat horizontal seems

5.1.13 secound coat one side of all corners

5.1.14...