Project Name | Huntsville Alabama Project | Project Number | 1 |

Project Manager | Shirley Bah | Prioritization | High |

Owner(s) | Walter Seitz | Start Date: | April 18, 2011 |

Scheduled Completion Date: | June 30, 2012 |

Mission | To undertake a project that will help Seitz corporation be at the top of the industry leader in plastic bottles and containers used mainly in the food and diary industry. |

|

Scope | The following deliverables are expected: * Select resources such as: Architect, Real Estate Consultant, and General Contractor * Recruit and Train Managers for Huntsville Plant * Create a Pre-Production and Production Plan * Create a Building Concept and Design * Procure Building Site, Permits and Appropriate Approvals * Construct the Huntsville Plant Building * Landscaping on Site * Personnel Recruiting for Plant Operations * Procure Equipment, Raw Material and Truck Fleet * Install Equipment * Create Product Distribution Plan and Pre-Production Plan * Start Up Production and DistributionThe following items are not expected to be part of this project: * Geothermal Heating * Solar Powered Electric Feed * Multi-Level Parking Garage * In-House Food Court * Construction of Separate Distribution Facility |

|

Objectives | To complete the construction of the new plant in Huntsville with a budget of $2,750,000 by April 18, 2011 and have it ready for full operation by June 30, 2012. |

|

Assumptions | Building permit and approval must be obtained before the start of construction. Plant location will be easily secured. Equipment and building materials should arrive on time at the construction site. Funding for the project should be ready for use by the start date. The labor market in Huntsville AL is sufficient in meeting staffing requirements of the new plant. |

|

Constraints | Required permit needed for construct may not be available on time. This could cause significant delay. Total budget for...