Background of A&D High Tech
A&D high-tech sell computer products and accessories to
consumers and small businesses. Development of the company‟s online store in 2002 as the company is loosing a competitive advantage without it Chris Johnson: strong experience as project manager Key factors:
Very short notice for project undertaking
Choice of “build” option for the platform
1
Project and Portfolio Management
Procedure for the MS project input
1) Write down the tasks
2)Insert predecessors and constraints
3) Insert resources (material + human resources) 4) Output the data
Task inputting
Inputting constraints Gantt Chart 2 Project and Portfolio Management
Project completion figures
From MS project (ignoring the sunk costs):
The project is due to finish on the 19/12/2014 if starting on
the 14/09/2012 for a total duration of 591 working days. Total project cost: $3,838,120
Labor Costs:$3,739,620 Capital Costs: $98,500
• $36,000 for the workstations (12) • $62,500 for the servers (5)
3
Project and Portfolio Management
Critical Path
Duration of Critical path = 164 Days
4
Project and Portfolio Management
Risk Assessment
Approach : Focus on the Critical Tasks Check if resources are fully allocated – this is a risk
situation Check for Tasks with multiple predecessors – higher the task dependency, higher the risk Check for longer tasks with multiple resources – these have maximum probability of going off the estimate
5
Project and Portfolio Management
Risk Assessment
Task Ids 16,26,20,54 have high dependency, these are high risk items and need
to be watched Tasks Ids 54,55,57,58 & 59 depend on multiple resources and have high risk Nearly 50% of critical tasks have high dependency on other resources or tasks, hence level of risk in the project is moderate to high
6 Project and Portfolio Management
Potential of Project to Complete on time
...