LAN/WAN
INTEGRATION PROJECT
3/6/2009
CIS 313 – Winter 2009 – Telecommunications and Networks
Submitted by Raymond Dawson
Integration of a LAN/WAN infrastructure that enables secure
transmission of data and information between four key business
locations.
LAN/WAN integration project
CIS 313 – WINTER 2009 – SUBMITTED BY RAYMOND DAWSON
P ROJECT SCENARIO ( BUSINESS SPECIFICATIONS ) :
As defined within the specifications document, the project plan involved the conceptual design of an integrated
LAN/WAN network that enabled secure transmission of data and information between four key business
locations/sites. The scope of the project included the following deliverables:
1. Development of a final LAN/WAN network diagram model that illustrates how transmission flows
between business locations.
2. Final project proposal consisting of 4-6 pages which includes diagrams, narratives, budget/cost
proposals and specific details regarding security and future growth.
3. Maintain project budget not to exceed $130,000.
Additional project guidance included:
Required LAN w/Bldg A in Skokie, have existing wired LAN only.
Expanding to 3 additional buildings. Each building’s internal network will be using an Ethernet wired or
wireless LANs: one facility in Chicago (Bldg B), the other facility in Lake Forrest (Bldg C) and the other
facility in Lombard (Bldg D).
Approximate Users in Bldg A = 39 users + 4 networked printers.
Approximate Users in Bldg B = 23 users + 3 networked printers.
Approximate Users in Bldg C = 9 users + 2 networked printers.
Approximate Users in Bldg D = 15 users + 3 networked printers with the potential to expand 15
additional users + 2 additional networked printers.
Bldg A DOES NOT have any Routers and will require WAN access to other new buildings. The other
three new facilities will also require access to each other and to Bldg A’s via a WAN.
Bldg A already has a server and Bldg B will...