Candy and Cane Destination Wedding
by
Wedding Crashers
~A Division of Wed-Away~
Alyssa Perry (Project Manager)
Jose Mayorga
Carrie Dubois
Antonio Alfieri
Mohamed Zouari
Contents
Project Scope Statement 5
Objective 5
Deliverables 5
Milestones 5
Technical Requirements 5
Limits and Exclusions 6
Customer Review 6
Work Breakdown Structure 7
Responsibility Matrix 8
Communications Plan 9
Purpose 9
Scope 9
Project Centralized Document Repository 9
External References 9
Document Maintenance 9
Communication Process 9
Informal 10
Formal 10
Status Meetings 10
Status Reports 10
Guidelines for Meetings 10
Meeting Agenda 10
Meeting Minutes 10
Action Items 11
Note Taker 11
Communication Escalation Process 11
Stakeholders Identification 11
Project Team Approval Signatures 12
Communication Schedule 13
Project Schedule 15
Project Budget 16
Budget Sources 20
Change Request 21
Assumptions & Dependencies 22
Risk Management Plan 22
Stakeholder Management Plan 24
Seating Chart 25
Entertainment 26
Project Scope Statement
Objective
To provide a successful destination wedding for Sugar Cane and Carl Candy in a Scottish Castle to be selected by the bride.
Deliverables
* Travel Arrangements
* Catered Events
* Venue Reservations
* Entertainment
* Flowers
* Lodging
* Remembrances
* Decorations
* Gifts
Milestones
* Decide on date-- No later than April 26, 2013
* Decide on budget-- No later than May 15, 2013
* Decide on venue-- No later than July 1, 2013
* Reserve castle-- Any date before July 12, 2013
* Confirm number of attendees-- Any date before July 12, 2013
* Purchase plane tickets-- No later than January 10, 2014
* Get hotel reservation confirmation-- No later than January 17, 2014
* Guests have proper docs/insurance-- No later than January 31, 2014
* Arrival brunch-- July 11, 2014
* Brides Maids' Luncheon--...