Assignment #3: Material Requirements Planning (MRP)

10% of Final Grade

This assignment is due at the end of Lesson 9 for marking.

Please show all of your calculations. This way you will receive partial marks in case your answer is incorrect.

1. What are the key inputs to successfully implement MRP? As a result of these inputs, which outputs are expected from MRP?

- The independent demand information.

- Parent-Component relationships from the BOM.

- Inventory status of final product and components.

- Planned order releases.

The visibility of these key inputs makes it easier to plane for the future requirements.

2. The bills of materials for two finished products (D and E), inventory status, and other relevant information are given below. Compute the planned order releases and projected on-hand balances for parts D, E and F.

[pic]

|Part D |1 |2 |3 |4 |5 |6 |

|Gross Requirements |7 |11 |9 |5 |8 |6 |

|Scheduled Receipts | | | | | | |

|Projected On-hand Inventory 10 |3 |22 |13 |8 |30 |24 |

|Planned Order Releases |30 | | |30 | | |

Q = 30; LT = 1; SS = 0

|Part E |1 |2 |3 |4 |5 |6 |

|Gross Requirements |10 |12 |15 |11 |6 |8 |

|Scheduled Receipts |...