Question | Answer |
(A) Regular Shirts | |
Theoretical CT for Cutting Operation with L of 60 | 0.25 minutes |
Theoretical CT for Cutting Operation with L of 10 | 0.56 minutes |
Labor Content in Cutting per shirt with L = 10 | 2.25 minutes |
Theoretical CT for Process with L = 60 | 0.50 min./shirt |
Daily Process Capacity with L = 60 | 960 shirts |
Average MLT for the process with current rate of 800 per day -- Minutes | 7056 minutes |
Average MLT for the process with current rate of 800 per day -- Days | 14.7 days |
Average Labor utilization for the process with current rate of 800/day | 69% (0.69) |
( C ) Mike’s Plan | |
Daily Capacity of the new ply machine | 960 shirts |
Average MLT for a shirt given 900 shirts per day | 2.2 days |
Average Labor Utilization with current rate of 900/day | 83% (0.83) |
( D ) Iike’s Plan | |
Daily process capacity for regular shirts | 720 shirts/day |
Daily process capacity for custom shirts | 123 shirts/day |
MLT for custom Line given 100/day | 230.40 minutes |
Labor utilization for Custom Line given 100/day | 34% (0.34) |
Executive Shirts Company Assignment: Detailed Calculations and Answers
(A) Regular Shirts:
I. Current Cutting Operation (Exbt. 2)
1. 60 layers of cloth (“L=60”)
Patterns for 8 shirts (8 shirts per layer)
Cutting takes: (1.5x L + 30) minutes for L layers
Number of shirts in L layers = 8L shirts
(Theoretical)CT for the cutting operation with 60 Layers= 120/480 = 0.25
Labor content per shirt in the cutting operation:
You could say that the labor content per shirt is 4 x 0.25 = 1 min, because the team of 4persons can cut one shirt every 0.25 minutes.
2. Effect of reduced L
Ex: L = 10
(Theoretical) CT (for L=10) = 1.5L+30 =1.5*10+30 = 45 minutes / (10*8= 80 shirts)= .5625...