PROJECT PLAN
TITLE AND SCOPE OF PROJECT
Title: LIBRARY MANAGAMENT SYSTEM
SCOPE:
The system accepts the General Library Transactions of book issue, return and renewals for the members
INITIAL ACTIVITY:
Project Plan
1. OUTPUTS OR DELIVERABLES FOR THE PROJECT:
| ITEM | REQUIREMENT | RESPONSIBILTY | PLANNED DATE | ACTUAL DATE | STATUS |
1. | Software | Turbo C | Vidhyalakshmi R., G. Vidhya, Roja Sanna Reddy, Shabnam Shaik | | | Completed |
2. | Documents | MS Word | Vidhyalakshmi R., Shabnam Shaik | | | Completed |
2. RESOURCE REQUIREMENTS
| RESOURCE NAME | WHY WE NEED A RESOURCE | WHERE WE GET THE RESOURCE FROM | HOW LONG WE NEED THE RESOURCE | HOW DO WE GET THE RESOURCE | CURRENT STATUS | CONTINGENCYACTION |
1 | Hardware | For construction of the system | St. Joseph’s College Of Engineering | Throughout the construction phase | Request the faculty | Available | Work At Home |
2 | Software | For construction of the system | St. Joseph’s College Of Engineering | Throughout the construction phase | Request the faculty | Available | Work At Home |
3. RISKS IDENTIFIED IN THE PROJECT
| RISKS | PROBABILITY (%) | SEVERITY (%) | ACTION PLAN |
1. | Missed Deadlines | 80 | 100 | Regular Discussion between the team and taking print outs |
2. | Defects in the end product due to problems during integration | 90 | 100 | Discuss the faculty and find the info from books and help |
3. | Difference in Standards followed like naming convention | 80 | 100 | Discuss the naming convention with members |
4. ALLOCATION OF TASKS
| TASKS | RESPONSIBILITY |
1. | Writing the source code for Library Management System | Vidhyalakshmi R., Vidhya G., Roja Sanna Reddy, Shabnam Shaik |
2. | Creating documents such as SRS, Abstract, Project plan | Vidhyalakshmi R., Vidhya G., Roja Sanna Reddy |
3. | Designing reports, E-R Diagrams,DFD,STD | Vidhya G., Shabnam Shaik |
SOFTWARE REQUIREMENT SPECIFICATION DOCUMENT
1. SCOPE...