Skill Builder 1

Submitted by: Submitted by

Views: 242

Words: 572

Pages: 3

Category: Business and Industry

Date Submitted: 11/23/2013 08:27 PM

Report This Essay

MGT 203 Name:______Xun Zhou__________

Skill Builder #1

1. In order to compete in a fencing tournament you have to go through the registration-approval process. You must be registered and sign waivers, have your ID checked to prove you have a fencing membership. Your weapons (foil, epee) need to be checked, your weapon wiring and cords get tested then you provide your mask to a tester who uses a tool to test durability. After everything is done you get a rubber stamp mark on the side of your mask. The process is presented below with the cycle time of each step shown in minutes:[pic]

a) (10 points) This process has a throughput time of _____5_____.

1) 4 minute

2) 2 minutes

3) 3 minutes

4) 12 minutes

5) 15 minutes

b) (10 points) Capacity of this process per hour is ____2_____.

1) 4 people

2) 15 people

3) 20 people

4) 30 people

5) 60 people

Some tournaments use this layout so that players can have their weapon and wiring tested at the same time:

[pic]

c) (10 points) This process has a cycle time of ____4______ per player.

1) 1 minute

2) 2 minutes

3) 3 minutes

4) 4 minutes

5) 12 minutes

d) (10 points) The steady-state capacity utilization for the ID check is ______1____.

1) 25%

2) 33%

3) 50%

4) 66%

5) 100%

Other tournaments use this layout:

[pic]

e) (10 points) Cycle time of this process is ___3______per player.

1) 2.5 minutes

2) 3 minutes

3) 4 minutes

4) 5 minutes

5) 6 minutes

f) (10 points) The steady-state utilization of Register and ID Check is _______5________. (hint: The steady-state utilization of a machine is the ratio of system capacity over the machine’s capacity, implying what the system can do versus what the machine can do.)

1) 50%

2) 66%

3)...